Recreation site improvements and maintenance of existing roads, water access, and day-use facilities to better accommodate and enhance the recreation opportunity
Location
Approximately three miles northwest of Noxon, Montana
Project timeline
1
Scoping Start
02/05/2020
2
Decision
04/2020 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Developed Site Management; Road Maintenance; Road Improvements/Construction |
| Triangle Pond Improvement Project | Decision Signed Date: 04/16/2020 |
| Forests | Kootenai National Forest |
| Districts | Cabinet Ranger District |
| Legal Land Description | Sec 9, 10 and Sec 15; T26N, R33W Montana Prime Meridian |