Project timeline

1
Scoping Start
07/02/2021
2
Decision
08/2022 (Estimated)
3
Implementation
08/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (19), 36 Cfr 220.6(E)(19)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Keeler Creek Side Channel PlugDecision Signed Date: 08/12/2022