Precommercial Thinning across the forest for vegetation improvement. Two decisions will be made. The hand felled units decision was completed on 01/19/2010. The plantation burning units decision is planned for 09/2010.
Location
Forest Wide
Project timeline
1
Scoping Start
01/23/2009
2
Comment Period
01/23/2009
3
Decision
02/2011 (Estimated)
4
Implementation
06/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| Forest Wide Precommercial Thin | Decision Signed Date: 01/12/2010 Legal Notice Date: 01/19/2010 |
| Forestwide Plantation Prescribed Burning | Decision Signed Date: 02/22/2011 Legal Notice Date: 02/25/2011 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Nez Perce-Clearwater National Forest All Units |