Commercially thin between 1,000-1,500 acres of previously managed plantations dating from the 1950’s through the early 1970’s using ground-based equipment.
Location
Lodge Point and Pine Knob area
Project timeline
1
Scoping Start
05/14/2010
2
Comment Period
06/30/2011
3
Decision
09/2011 (Estimated)
4
Implementation
12/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Green); Watershed Improvements |
| Lodge Point Project | Decision Signed Date: 09/30/2011 Legal Notice Date: 10/04/2011 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Nez Perce-Clearwater National Forest All Units |
| Legal Land Description | T32N R6E Sections 13-17, 20-30 |