The Clearwater Ranger District of the Nez Perce National Forest proposes to remove the existing felled material using ground based equipment skidding, decking and processing within the existing road prism accessing the Castle Creek Work Center.
Location
Castle Creek Work Center facility located on the Clearwater Ranger District, Nez Perce National Forest, Idaho County
Project timeline
1
Scoping Start
01/18/2011
2
Comment Period
01/18/2011
3
Decision
05/2011 (Estimated)
4
Implementation
07/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Facility Maintenance; Timber Sales (Salvage); Watershed Improvements |
| Castle Creek Work Center Maintenance Decision Memo | Decision Signed Date: 05/25/2011 Legal Notice Date: 05/31/2011 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Clearwater Ranger District |
| Legal Land Description | T29N R4E Sections 21 and 28 (Boise Meridian) |