The Salmon River Ranger District proposes to authorize Mr. Robert Martin, the operator, to remove a one-yard bulk sample from a caved adit and an existing shallow pit, and to extract a channel sample of material between the adit and pit.
Location
Rubie Creek, Salmon River Ranger District
Project timeline
1
Scoping Start
01/12/2010
2
Decision
02/2011 (Estimated)
3
Implementation
06/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Max #1 Lode Exploration Decision Memo | Decision Signed Date: 02/17/2011 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Salmon River Ranger District |
| Legal Land Description | T25N R3E Section 12 |