The Red River Ranger District proposes to reissue a special use permit to Sibyl Ward for an existing 4 foot by 4 foot spring box and a one inch diameter 415 foot water transmission line which crosses National Forest system lands to her residence.
Location
National Forest system lands near the town of Dixie, Idaho
Project timeline
1
Scoping Start
06/15/2012
2
Decision
07/2012 (Estimated)
3
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Red River Ranger District |
| Legal Land Description | T26N R8E Section 27 |