The project proposes to decommission approximately 41 miles of unneeded Forest system roads and 25 miles of non-system skid trail/log jammer roads in the Lolo Creek watershed.
Location
The area lies about 12 miles east of Kamiah, Idaho in Idaho and Clearwater counties.
Project timeline
1
Scoping Start
11/04/2013
2
Comment Period
08/01/2014
3
Objection Period Start
02/11/2015
4
Decision
04/2015 (Estimated)
5
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning |
| Lolo First 50 Road Decommissioning Project Final Decision Notice | Decision Signed Date: 04/07/2015 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Lochsa Ranger District |
| Legal Land Description | T33N, R5E and R6E; T34N, R5E, R6E, R7E; T35N, R5E, R6E, and R7E; T36N, R5E, R6E and R7E |