The Moose Creek District is considering activities within the Middle Fork Clearwater drainage to increase early successional habitats; increase resilient tree speces; and protect aquatic species.
Location
Project area is on the south side of the Middle Fork Clearwater River and extends from the Forest boundary (approximately 2.5 miles southwest of the community of Syringa) upstream to Lowell.
Project timeline
1
NOI in Federal Register
01/03/2014
2
DEIS NOA in Federal Register
10/2014 (Estimated)
3
FEIS NOA in Federal Register
09/2015 (Estimated)
4
Decision
10/2015 (Estimated)
5
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green); Watershed Improvements |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Moose Creek Ranger District |
| Legal Land Description | Township 32 North, Range 6 East Sections 3, 4, 5, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 22, 23, 25, 26 and Township 32 North, Ranger 7 East, Sections 7, 8, 17, 18 Boise Meridian |