Project would decommission approximately 65 miles of non-system roads in the Clear Creek watershed. These roads are currently not open to public access and are not needed for future land management activities.
Location
The project area lies about seven miles east of Kooskia, Idaho in the norther half of the Clear Creek watershed
Project timeline
1
Scoping Start
03/31/2014
2
Decision
01/2015 (Estimated)
3
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Watershed Improvements |
| Clear Ridge Non-System Road Decommissioning Project | Decision Signed Date: 01/14/2015 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Moose Creek Ranger District |
| Legal Land Description | T31N, R6E and T32N, R6E, Idaho and Clearwater Counties, Idaho |