Repairs will be performed on the Gedney Bridge.
Location
Gedney Bridge on the Selway Road, NFS Road 223.
Project timeline
1
Scoping Start
05/01/2014
2
Decision
07/2014 (Estimated)
3
Implementation
12/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Gedney Creek Bridge Repairs Decision Memo | Decision Signed Date: 07/16/2014 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Moose Creek Ranger District |
| Legal Land Description | T31N, R9E, Section 3 NE 1/4 (Boise Meridian). |