The earthen fill at the blown out dams and outlets from the dam and ponds are failing, and the stream's flow is seeping through eroding existing material. Restore riparian areas.
Location
Please see Map in Scoping Letter
Project timeline
1
Scoping Start
12/30/2014
2
Decision
11/2024 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Red River Ranger District |
| Legal Land Description | Allison - Blown out Dam: T29N, R7E, SE 1/4 of NE 1/4 of S16; Dam/Pond below FS Road #9874: T29N, R7E, NE 1/4 of NE 1/4 of S21; Dam/Pond east of FS Road #307I: T29N, R7E, NE 1/4 of SE 1/4 of S21 |