The North Fork Ranger District proposes to approve the claimant's proposal to explore underground in an existing shaft, which has several tunnels in the French Mountain area.
Location
North Fork Clearwater River (French and Orogrande Creeks)
Project timeline
1
Scoping Start
05/29/2012
2
Decision
07/2018 (Estimated)
3
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | North Fork Ranger District |
| Legal Land Description | T37N, R6E, Section 34 |