Avista proposes to install 5000' of buried electrical line and mount three junction enclosures at ground level along Road 222D. Work would be done in summer/fall 2016, and is projected to take one week to complete.
Location
T25N, R8E, Sections 3, 10, 11, Idaho County, ID
Project timeline
1
Scoping Start
05/27/2016
2
Decision
09/2016 (Estimated)
3
Implementation
10/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Avista Buried Electrical Lines | Decision Signed Date: 09/20/2016 |