Decision Memo Completed

Avista Buried Electrical Lines

Nez Perce-Clearwater National Forests Idaho, Idaho Red River Ranger District

Avista proposes to install 5000' of buried electrical line and mount three junction enclosures at ground level along Road 222D. Work would be done in summer/fall 2016, and is projected to take one week to complete.

Location

T25N, R8E, Sections 3, 10, 11, Idaho County, ID

Project timeline

1
Scoping Start
05/27/2016
2
Decision
09/2016 (Estimated)
3
Implementation
10/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Avista Buried Electrical LinesDecision Signed Date: 09/20/2016
ForestsNez Perce-Clearwater National Forest
DistrictsRed River Ranger District
Legal Land DescriptionNot Applicable
Special use management