Replace existing timber bridge with steel stringer bridge. Reconstruct 100 ft. of NF Trail 821 surrounding site to align bridge approaches. Rehab and close unauthorized ford using local native vegetation. To be started in 2017 or 2018.
Location
Township 28 North, Range 7 East, Section 36; County 233 road (milepost 10.5); Idaho County, Idaho
Project timeline
1
Scoping Start
03/28/2017
2
Decision
06/2017 (Estimated)
3
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Five Mile ATV Bridge Replacement | Decision Signed Date: 06/08/2017 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Red River Ranger District |
| Legal Land Description | Not Applicable |