The claimant proposes exploratory drilling on the Red River RD to test for gold values. The project area is in previously disturbed and undisturbed areas of the Baner Creek drainage. The proposal includes 11 drill sites with 2 holes max/site.
Location
Township 28 North, Range 8 East, Section 18; Idaho County, Idaho
Project timeline
1
Scoping Start
06/30/2017
2
Decision
10/2017 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Baner Group Exploration Drilling | Decision Signed Date: 10/03/2017 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Red River Ranger District |
| Legal Land Description | Not Applicable |