Thin approximately 472 acres of trees in overstocked previously harvested stands. Work completed by contract crews under FS oversight and by FS personnel. All work to be done by hand using chainsaws. Access to the treatment sites on existing roads.
Location
Multiple (25) stands on the North Fork Ranger District, Clearwater County, Idaho.
Project timeline
1
Scoping Start
03/31/2018
2
Decision
04/2018 (Estimated)
3
Implementation
04/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Pre-Commercial Thinning - North Fork | Decision Signed Date: 04/19/2018 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | North Fork Ranger District |
| Legal Land Description | Not Applicable |