To restore stream and riparian function in Musselshell Meadows, four beaver dam analogs would be constructed, using locally gathered materials, along a 1/4 mile of Musselshell Creek. All work to be done by hand with access to the sites by foot.
Location
Township 35 North, Range 6 East, Section 20
Project timeline
1
Scoping Start
03/31/2018
2
Decision
07/2018 (Estimated)
3
Implementation
09/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Musselshell Restoration Beaver Dam Analogs | Decision Signed Date: 07/12/2018 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Lochsa/Powell Ranger District |
| Legal Land Description | Not Applicable |