Potlatch Corp. proposes to expand the Bovill Source. Approx. 8 to 12 test pits (250 ft. squ. x 15 ft. deep) would be excavated and a total of 15 to 24 holes drilled from 30 to 60 ft. in depth. Up to 45 trees would be removed for creation of the pits.
Location
Township 40 North, Range 1 West, Section 1; Latah County, Idaho
Project timeline
1
Scoping Start
02/15/2018
2
Decision
03/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Bovill Source | Decision Signed Date: 03/12/2018 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Palouse Ranger District |
| Legal Land Description | Not Applicable |