Commercial harvest & non-commercial fuels treatments to improve species/age class diversity & forest health and reduce potential fire behavior in WUI. Build temp. rds. Site prep. Reforest harvest units. Road Maintenance for watershed improvement.
Location
sections 4, 8, 9, 10, 14, 15, 16, 17, 21, 22, 23, 24, 26, 27, 34 and 35, T43N, R3W, Boise Meridian and portions of sections 2, 3, 11, TT42N, R3W, Boise Meridian
Project timeline
1
Scoping Start
09/28/2018
2
Comment Period
09/28/2018
3
Objection Period Start
10/30/2020
4
Decision
04/2021 (Estimated)
5
Implementation
03/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| White Pine | Decision Signed Date: 04/20/2021 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Palouse Ranger District |
| Legal Land Description | Not Applicable |