Construct a new office on FS administrative site: relocate the 2 annexes adjacent to the bunkhouse; construct new SO building, parking areas for employee/public and fleet security, and an access path & road linking lower and upper portions of site.
Location
Township 33 North, Range 3 East, Section 1; Kamiah, Lewis County, Idaho
Project timeline
1
Scoping Start
07/06/2019
2
Comment Period
07/06/2019
3
Decision
02/2020 (Estimated)
4
Implementation
03/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction |
| New Kamiah Supervisor's Office | Decision Signed Date: 02/07/2020 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Nez Perce-Clearwater National Forest All Units |
| Legal Land Description | Not Applicable |