Fall and leave, or fall and remove, any dead, dying, or structurally unsound trees within the project area. Felling/removal is proposed for up to a maximum of 165 feet (50 meters) from either edge of the road surface, unless otherwise indicated.
Location
Treatments would occur Forestwide, only on specified road segments.
Project timeline
1
Scoping Start
09/13/2020
2
Comment Period
12/2022 (Estimated)
3
Objection Period Start
02/2023 (Estimated)
4
Decision
05/2023 (Estimated)
5
Implementation
05/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Road Maintenance |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Nez Perce-Clearwater National Forest All Units |
| Legal Land Description | Not Applicable |