Decision Memo Completed

O'hara Bridge 651-01 Replacement

Nez Perce-Clearwater National Forests Clearwater, Idaho Moose Creek Ranger District

Replace existing 74 foot two-span bridge with 134 foot channel spanning bulb-tee bridge designed to handle 100 year flows. Current bridge has increased risk of failure and impedes movement of large debris.

Location

T32N, R7E, Section 25

Project timeline

1
Scoping Start
05/07/2021
2
Decision
03/2024 (Estimated)
3
Implementation
07/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Improvements/Construction; Watershed Improvements
O'hara Bridge 651-01 ReplacementDecision Signed Date: 03/22/2024