Rd decomm to facilitate meadow restoration along W Fk Potlatch River. Rd construction to maintain access to FSR 377 and trail relocation to improve public safety; improve parking. Requesting EAD under IIJA, comment period per IIJA offered if granted.
Location
Junction of West Fork Potlatch River and Feather Creek along FSR 377.
Project timeline
1
Scoping Start
12/2025 (Estimated)
2
Decision
05/2026 (Estimated)
3
Implementation
05/2026 (Estimated)
NEPA / regulatory detail
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Developed Site Management; Fuel Treatments (Non-Activity Fuels); Trail Management; Road Improvements/Construction; Grazing Structural Improvements; Watershed Improvements |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Palouse Ranger District |
| Legal Land Description | Not Applicable |