Decision Memo Completed

Partridge Creek Crossing

Nez Perce-Clearwater National Forests Clearwater, Idaho Palouse Ranger District

The project will replace the existing three culverts and one side channel culvert currently channeling Partridge Creek across FSR 4743 with appropriate AOP drainage structures.

Location

FSR 4743

Project timeline

1
Scoping Start
09/09/2024
2
Decision
10/2024 (Estimated)
3
Implementation
05/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Road Improvements/Construction; Watershed Improvements
Partridge Creek CrossingDecision Signed Date: 10/29/2024
ForestsNez Perce-Clearwater National Forest
DistrictsPalouse Ranger District
Legal Land DescriptionNot Applicable
Watershed managementRoad management