Remove or modify 11 existing dam embankments, and complete wetland and stream restoration within Allison Creek and Ericson Creek watersheds.
Location
Allison Creek watershed is located 8 miles west of Elk City, Idaho. Ericson Creek watershed is located 6 miles northwest of Elk City, Idaho.
Project timeline
1
Scoping Start
10/11/2024
2
Decision
12/2024 (Estimated)
3
Implementation
04/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Allison and Ericson Dams Removal | Decision Signed Date: 12/20/2024 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Red River Ranger District |
| Legal Land Description | Not Applicable |