Environmental Assessment Completed

Wyoming Department of Transportation WYOLINK Duncan Lake Communications Site

Bighorn National Forest Sheridan, Wyoming Tongue Ranger District

WYDOT has submitted a proposal for a new multi-user communications site to include approx. 18534’ of underground powerline, 150’ tower, pre-fab building and access road off of FSR 233 to proposed site.

Location

Near Duncan Lake off of FSR 233

Project timeline

1
Scoping Start
11/16/2009
2
Comment Period
06/05/2010
3
Decision
07/2010 (Estimated)
4
Implementation
08/2010 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Duncan Lake Communication Site ProjectDecision Signed Date: 07/20/2010
ForestsBighorn National Forest
DistrictsTongue Ranger District
Legal Land DescriptionSec. 16-18 T. 54N., R. 88W, 6th P.M.