Convert overhead powerline to underground powerline located at the Medicine Wheel Communication site.
Location
Powerline runs from Medicine Mountain Communication Site down the ridge to the west crossing Forest Developed Road #12 and ties into the current underground line near Forest Developed Road #13.
Project timeline
1
Scoping Start
07/01/2011
2
Decision
09/2011 (Estimated)
3
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Rocky Mountain Power Special Use Permit Amendment #1 | Decision Signed Date: 09/15/2011 |
| Forests | Bighorn National Forest |
| Districts | Medicine Wheel Ranger District |
| Legal Land Description | T56N, R92W, Sections 22, 23, and 24 |