Decision Memo Completed

Lovcom tower at Bosin Rock Communitcation Site

Bighorn National Forest Sheridan, Wyoming Tongue Ranger District

Application from Lovcom to install new 40 foot tower to accomodate additional use at site. This decision will comply with direction to offer 30-day notice-and-comment and appeal opportunities, as appropriate.

Location

Bosin Communication Site

Project timeline

1
Scoping Start
03/05/2012
2
Comment Period
04/03/2012
3
Decision
05/2012 (Estimated)
4
Implementation
06/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Lovcom, INC. Tower InstallationDecision Signed Date: 05/18/2012 Legal Notice Date: 05/25/2012
ForestsBighorn National Forest
DistrictsTongue Ranger District
Legal Land DescriptionT54N. R85W. Sec 29
Special use management