Reissue Special Use Permit to WYDOT for the Burgess Junction Maintenance camp for a new 20-year term.
Location
Located at Junction of US HWY 14 and HWY 14a
Project timeline
1
Scoping Start
11/14/2014
2
Decision
12/2014 (Estimated)
3
Implementation
01/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Wyoming Department of Transportation Reissuance of Special Use Permit | Decision Signed Date: 12/17/2014 |
| Forests | Bighorn National Forest |
| Districts | Tongue Ranger District |
| Legal Land Description | Section 1, T.55N, R.89W |