Decision Memo Completed

Ponty Special Use Permit Reissuance

Bighorn National Forest Sheridan, Wyoming Bighorn National Forest All Units

Reissuance of existing Special Use Permit for a new term authorizing the continued use and maintenance of a spring development and associated waterline.

Location

Spring development is located off Forest Service Road #287, waterline runs to the south to the private inholding near Big Goose.

Project timeline

1
Scoping Start
05/06/2016
2
Decision
06/2016 (Estimated)
3
Implementation
06/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Ponty Waterline Special Use Permit ReissuanceDecision Signed Date: 06/10/2016
ForestsBighorn National Forest
DistrictsTongue Ranger District
Legal Land DescriptionT54N, R86W, Section 30
Special use management