Reissuance of existing Special Use Permit for a new term authorizing the continued use and maintenance of a spring development and associated waterline.
Location
Spring development is located off Forest Service Road #287, waterline runs to the south to the private inholding near Big Goose.
Project timeline
1
Scoping Start
05/06/2016
2
Decision
06/2016 (Estimated)
3
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Ponty Waterline Special Use Permit Reissuance | Decision Signed Date: 06/10/2016 |
| Forests | Bighorn National Forest |
| Districts | Tongue Ranger District |
| Legal Land Description | T54N, R86W, Section 30 |