Wyoming Dept of Transportation seeks authorization to install landslide monitoring equipment outside right of way along US Highway 14A
Location
Highway 14A at approximately Mile Post 84.65
Project timeline
1
Scoping Start
10/05/2016
2
Decision
10/2016 (Estimated)
3
Implementation
10/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Wyoming Dept of Transportation installation of landslide monitoring equipment off US Highway 14A | Decision Signed Date: 10/06/2016 |
| Forests | Bighorn National Forest |
| Districts | Medicine Wheel Ranger District |
| Legal Land Description | Section 11, T. 55N., R. 91 W, 6th PM |