Decision Memo Completed

Antelope Butte Water Development

Bighorn National Forest Big Horn, Wyoming Bighorn National Forest All Units

Antelope Butte Foundation has submitted a special use application to construct a new springbox at an existing developed spring site with current water rights and install a new waterline to provide year round domestic water at the permitted facilities

Location

Spring site is located to the southeast of the lodge at the ASP & Murphy Spring.

Project timeline

1
Scoping Start
09/16/2016
2
Decision
07/2017 (Estimated)
3
Implementation
09/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Antelope Butte Water DevelopmentDecision Signed Date: 07/17/2017
ForestsBighorn National Forest
DistrictsMedicine Wheel Ranger District
Legal Land DescriptionNot Applicable
Special use management