Wyoming Game & Fish Dept. proposal to renovate its authorized rip-rap dam on South Piney Creek which diverts water to the Mead Coffeen Irrigation District's crossover ditch and the Story Fish Hatchery to maintain flows and repair degradation.
Location
1/2 mile from Story Fish Hatchery on South Piney Creek
Project timeline
1
Scoping Start
03/12/2018
2
Decision
07/2018 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Special Use Authorizations |
| Mead-Coffeen Diversion Dam Rehab | Decision Signed Date: 07/02/2018 |
| Forests | Bighorn National Forest |
| Districts | Tongue Ranger District |
| Legal Land Description | Section 23, T. 53N., R 84W. 6th P.M. |