The Shell Falls Re-Powering Project will replace the existing underground power line that runs up Shell Canyon for 4 miles from Shell Falls Visitor Center.
Location
Shell Falls Visitor Center T. 53 N. R.89 W. Sec 7
Project timeline
1
Scoping Start
03/11/2021
2
Decision
07/2021 (Estimated)
3
Implementation
08/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Shell Falls Re-Powering | Decision Signed Date: 07/29/2021 |
| Forests | Bighorn National Forest |
| Districts | Medicine Wheel Ranger District |
| Legal Land Description | Not Applicable |