Forest Service proposes to authorize the Operating Plan, within the context of the statutory rights under Federal mining laws.
Location
End of FSR 405
Project timeline
1
Scoping Start
03/04/2022
2
Comment Period
04/01/2022
3
08/16/2022
4
Decision
08/2022 (Estimated)
5
Implementation
09/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Mud Mine | Decision Signed Date: 08/16/2022 |
| Forests | Bighorn National Forest |
| Districts | Powder River Ranger District |
| Legal Land Description | T 49N R 87W Section 13 |