Decision Memo Completed

FSR 17 Paintrock Road Improvements

Bighorn National Forest Big Horn, Wyoming Medicine Wheel Ranger District

Improvements on approximately 6 miles of Forest Service Road 17 including culvert replacements, road surface reconditioning, installation of drivable dip, individual tree removals and switchback widening.

Location

Work begins at the intersection with US Hwy 14 and continue southwest crossing Shell Creek and ending at the Forest Boundary south of Snowshoe Pass, does not include the segment across private land.

Project timeline

1
Scoping Start
04/05/2022
2
Comment Period
05/27/2022
3
06/15/2022
4
Decision
06/2022 (Estimated)
5
Implementation
07/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (23), 36 Cfr 220.6(E)(23)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Road Improvements/Construction
FSR 17 Paintrock Road ImprovementsDecision Signed Date: 06/15/2022
ForestsBighorn National Forest
DistrictsMedicine Wheel Ranger District
Legal Land DescriptionT53N, R89W, Sec 14, 23, 24 and T53N, R88W, Sec 19, 30, 31
Road management