Construction of permanent pipe corral in the Big Spring pasture of the Salt Creek Allotment. This location is on Hwy 14, one mile south of Granite Pass. The corral would be approx. 200 x 200 feet in size, only used by grazing permittees.
Location
T54N, R88W, E 1/2 Sec 30
Project timeline
1
Scoping Start
04/07/2022
2
Decision
10/2022 (Estimated)
3
Implementation
12/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management |
| Forests | Bighorn National Forest |
| Districts | Medicine Wheel Ranger District |
| Legal Land Description | Not Applicable |