Upgrade and update the River Cabin for the facility to meet facility to meet Architectural Barriers Act (ABA) standards, replace the degrading toilet facility and provide a parking area and a hardened trail for access to the facility.
Location
half mile up FSR 27 on the south side
Project timeline
1
Scoping Start
05/11/2023
2
Decision
12/2024 (Estimated)
3
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| River Cabin FLREA Rental Upgrades | Decision Signed Date: 12/04/2024 |
| Forests | Bighorn National Forest |
| Districts | Powder River Ranger District |
| Legal Land Description | Not Applicable |