Re-construct an existing overhead 69kV transmission power line that was damaged during the Myrtle Fire, July 2012.
Location
South of Pringle, South Dakota
Project timeline
1
Scoping Start
11/14/2012
2
Comment Period
11/14/2012
3
Decision
01/2013 (Estimated)
4
Implementation
01/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Overhead Power Line Rebuild Project | Decision Signed Date: 01/18/2013 |
| Forests | Black Hills National Forest |
| Districts | Hell Canyon Ranger District |
| Legal Land Description | Sections 18, 19, 30, & 31, T5S, R5E; Sections 5, 6, 8, & 17, T6S, R5E |