Decision Memo Completed

Deadwood-Agnew Mine Reclamation Project

Black Hills National Forest Custer, South Dakota Hell Canyon Ranger District

The area to be reclaimed is approximately 4.4 acres. The mines open pit will be filled with a mica reclamation product that is produced at Pacer Corp. Once the pit is filled topsoil will be applied and the area will be seeded.

Location

The project is located approximately 1.5 miles west of Custer, SD and 0.2 miles south of US Hwy 16A

Project timeline

1
Scoping Start
06/28/2013
2
Comment Period
06/28/2013
3
Decision
01/2014 (Estimated)
4
Implementation
03/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityAbandoned Mine Land Clean-Up
Deadwood-Agnew Mine Reclamation ProjectDecision Signed Date: 01/14/2014
ForestsBlack Hills National Forest
DistrictsHell Canyon Ranger District
Legal Land DescriptionBlack Hills Meridian, T3S, R5E, SE 1/4, Section 20
Minerals and geology