To amend the existing Plan of Operations for Pacer Corporation. Involves constructing an alterante access and loading area, reconstruct existing access. Some merchantable trees would need to be removed to clear the area.
Location
T4S R4E SE 1/4 Section 36
Project timeline
1
Scoping Start
04/06/2013
2
Decision
06/2013 (Estimated)
3
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Black Hills National Forest |
| Districts | Hell Canyon Ranger District |
| Legal Land Description | T4S R4E SE1/4 of Section 36 |