Decision Memo Completed

Black Hills Electric Cooperative 306 & 314 Projects

Black Hills National Forest Custer, South Dakota Hell Canyon Ranger District

The Black Hills Electric Cooperative is requesting to replace portions of their single-phase line with three-phase lines. Line reconstruction will include replacement of all poles within the corridor.

Location

Segment of line from Custer to Pringle on the West side of highway 385.

Project timeline

1
Scoping Start
02/11/2019
2
Decision
08/2019 (Estimated)
3
Implementation
09/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Black Hills Electric Cooperative 306 & 314 ProjectsDecision Signed Date: 08/23/2019