Installation of an underground utility line. Three options for the path of the line are being evaluated, one of which will be selected for implementation.
Location
Approximately 4.6 miles southeast of Deadwood SD. About 1/10th mile northeast of the end of Country Club Road, Branch 1C
Project timeline
1
Scoping Start
06/07/2021
2
Decision
08/2021 (Estimated)
3
Implementation
08/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| M.S. 1904 Utility Line Installation | Decision Signed Date: 08/23/2021 |
| Forests | Black Hills National Forest |
| Districts | Northern Hills Ranger District |
| Legal Land Description | T4N R3E Section 19 NW 1/4 and T4N R3E Section 24 SW 1/4 BHM |