Special use authorization for existing 230-kV and 69-kV electrical powerlines, including Wyodak-Hot Springs and Tekla-Osage-Rapid City lines.
Location
Thunder Basin NG and Black Hills NF.
Project timeline
1
Scoping Start
05/30/2018
2
Decision
06/2018 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Reauthorization of 230-kV and 69-kV Power Lines and Rights-of-Way | Decision Signed Date: 06/14/2018 |
| Forests | Black Hills National Forest; Medicine Bow-Routt National Forest |
| Districts | Hell Canyon Ranger District; Douglas and Thunder Basin Ranger District |
| Legal Land Description | T41N R71W, T42N R71W, T43N R71W, T43N R72W, T44N R69W, T44N R70W; AND T46N R63W, T47N R63W, T47N R64W, T47N R65W, T48N R65W, T48N R66W |