Decision Memo Completed

SDN Fiber Optic Installation - Phase II

Black Hills National Forest Lawrence; Pennington, South Dakota Northern Hills Ranger District

SDN is expanding their fiber optic network to provide high speed internet service to rural areas. Phase II of the project would install fiber optic line and towers along Hwy 385 from Hill City to Lead.

Location

Fiber optic line would be buried within the US Hwy 385 corridor. Six towers would be constructed NFS land along the corridor from Hill City to Lead.

Project timeline

1
Scoping Start
08/02/2022
2
Decision
07/2023 (Estimated)
3
Implementation
08/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
SDN Fiber Optic Installation - Phase IIDecision Signed Date: 07/13/2023
ForestsBlack Hills National Forest
DistrictsNorthern Hills Ranger District
Legal Land DescriptionNot Applicable
Special use management