SU permit request for a 60'x75' ROW to provide access to reach the W boundary of the Cornerstone Sub. property. Access to be used by Hideout Lake Sub.& 3 adjacent owners. 2 existing routes to be obliterated & reclaimed w/completion of single entrance
Location
On the Ouray Ranger District, Uncompahgre National Forest.
Project timeline
1
Scoping Start
09/30/2007
2
Decision
02/2009 (Estimated)
3
Implementation
06/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Memo | Decision Signed Date: 02/25/2009 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Ouray Ranger District |