The project involves installing new interpretive signs, stabilizing historic stone structures, stabilizing the stone west portal and entrance to the Alpine Tunnel, and some rerouting sections of trail.
Location
Alpine Tunnel, Gunnison Ranger District, GMUG NF
Project timeline
1
Scoping Start
08/10/2009
2
Decision
09/2009 (Estimated)
3
Implementation
07/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Heritage Resource Management; Trail Management |
| Alpine Tunnel - ARRA | Decision Signed Date: 09/21/2009 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Gunnison Ranger District |
| Legal Land Description | Alpine Tunnel |