Decision Memo Completed

Whitepine-Salida Powerline Reconstruction

Grand Mesa, Uncompahgre and Gunnison National Forests Gunnison, Colorado Gunnison Ranger District

Replace poles and line on the existing permitted alignment.

Location

Whitepine townsite west to Salida Ranger District

Project timeline

1
Scoping Start
05/15/2012
2
Comment Period
05/15/2012
3
Decision
07/2013 (Estimated)
4
Implementation
10/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Whitepine-Salida Powerline ReconstructionDecision Signed Date: 07/23/2013 Legal Notice Date: 07/23/2013
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsGunnison Ranger District
Special use management