Project timeline

1
Scoping Start
03/28/2013
2
Comment Period
03/28/2013
3
Decision
07/2013 (Estimated)
4
Implementation
08/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityTrail Management
West Double Top Trail ProjectDecision Signed Date: 07/02/2013 Legal Notice Date: 07/02/2013
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsGunnison Ranger District
Legal Land DescriptionR 85W, T 14S, Sections 10, 11, 14, 15
Recreation management